Gas adjustment (Conversion to LPG)
All work must be carried out by a CORGI registered
engineer.
IMPORTANT: Always isolate the cooker from the electricity
supply before changing the injectors and/or adjusting the
minimum flow of the burners.
o Remove the pan-stands, burners and
flame spreaders (A).
o Unscrew the injector (B) and replace it
with the stipulated injector for the new gas
supply (see table below).
o Reassemble all the burners carefully; in particular you should
make sure that the flame spreader is correctly placed on the
burner.
o IMPORTANT: The minimum flow adjustment process must
be completed before the appliance is next used.